I/I Evaluation - Basins CC-16, CC-20, WP-6
Study Schedule
|
|
|
External Building Inspections and CCTV Sewer Inspections.
Wade - CH2M Hill and Archer Engineers are conducting external building inspections and closed-circuit televising of sanitary sewers in the Lee's Summit Study Area. See Study
Areas below. This work is scheduled to begin July 16, 2007. Crews
will perform the inspections between the hours of 8:00 to 5:00 Monday through Friday as weather permits. Some Saturday testing may occur. For more information about building inspections see: Building Survey FAQ.
|
Smoke Testing. Wade - CH2M Hill and Archer Engineers field technicians will soon begin smoke testing sanitary sewer lines in
the Lee's Summit Study Area. See Study Areas below. Crews
will perform the tests between the hours of 8:00 to 5:00 Monday through Friday as weather permits. Some Saturday testing may occur.
Smoke testing is scheduled to begin August 13, 2007. For more information on the smoke testing process see: Smoke
Test FAQ.
|
| |
| Download Press Release
|
|
|
|
|
|
|
|